SL.NO |
PROJECT DETAILS |
COMPLETION TIME |
DISCIPLINE COVERED |
|
COMPLETION TIME-SCHEDULE |
COMPLETION TIME-ACTUAL |
|
1 |
Contract No. : 10327 Our Ref. : SC-2043 Client : KOC |
|
Maintenance and Engineering Services to Rosemount RS3 Control system installed in Gathering Centers of Kuwait Oil Co. (KOC). |
24/02/2000 |
23/02/2006 |
Instrumentation |
|
2 |
Contract No. : 98GO57 Our Ref. : SC-2040 Client : KOC |
|
Maintenance services to Oil Production Facilities of Kuwait Oil Co. in North & West Kuwait areas in the Disciplines of Mechanical, Electrical & Instrumentation. |
15/9/2003 |
15/09/2005 |
Mechanical, Electrical & Instrumentation |
|
3 |
Project : 98-30047 SC-2037 Client : EQUATE |
|
Instrument & Electrical Maintenance works in EQUATE Poly-ethylene plant. |
2000-2004 |
2000-2004 |
Instrumentation & Electrical |
|
4 |
Projects : 3260622 SC-2040A Client : PIC |
|
Maintenance of Instrumentation &Laboratory Equipments in Petrochemical Industries Co. (PIC) Plant at Shuaiba. |
2003-2004 |
2003-2004 |
Instrumentation |
|
5 |
Project : MEW/AS/1814-97/98 SC-2036 Client : MEW (DEPS) |
|
Electrical Maintenance to Doha East Power Station of MEW, including overhaul of 3.3 KV to 11 KV Motors, Switchgear systems, MCC Operations & Fire Alarm Systems. |
1998-2001 48 months |
1998-2001 48 months |
Electrical |
|
6 |
Project : CS-1111 / SH-91-43 / CT-4111 / CT-3520 / CT-2080 / CT-1410 SC-2002 Client : KNPC-S |
|
Maintenance of Process Control Instrumentation which includes On-line Analysers as well as Laboratory Analytical Instruments at Shuaiba Refinery, KNPC |
1982-2001 |
1982-2001 |
Instrumentation |
|
7 |
Project : CB-0604 / CB-0957 / CB-1088 SC-2031 Client : KNPC-MAB |
|
Maintenance of Laboratory Analyzers Preventive and Corrective Maintenance of 136 lab. Analyzers including Modifications & Training of KNPC Personnel in MAB Refinery |
1996-2001 (108 months) |
1996-2001 (108 months) |
Instrumentation |
|
8 |
Project : 97A018 SC-2029 Client : KOC |
|
Maintenance and Engineering services of Rosemount RS-3 Distributed Control System at KOC Gathering Centre Nos.1,3,4,6,7,8,16,19 and 21and Training Simulation Unit at Production Operations Training Centre in Burgan. |
1997-2001 (48 months) |
1997-2001 (48 months) |
Instrumentation |
|
9 |
Project : CB/0690 SC-2032 Client : KNPC-MAB |
|
Maintenance of Fire Alarm & Siren System in Mina Abdullah Refinery. |
1997-2001 (48 months) |
1997-2001 (48 months) |
Electrical |
|
10 |
Project : CB/0704 SC-2033 Client : KNPC-MAB |
|
Maintenance of the Halon System at KNPC Mina Abdullah Refinery |
1996-2000 39 months |
1996-2000 39 months |
Electrical |
|
11 |
Project : 93G024 SC2027 Client : KOC |
|
Mechanical Maintenance Services to Oil Production Facilities in all Operational Areas of Kuwait Oil Co. |
1993-1997 (48 months) |
1993-1997 (48 months) |
Mecahnical |
|
12 |
Project : 94A007 SC-2029 Client : KOC |
|
Testing, Calibration/Repair of Specialised RS-3 Rosemount DCS for 13 systems and SCADA Telemetry Systems. |
1994-1997 36 months |
1994-1997 36 months |
Instrumentation |
|
13 |
Project : SC-2028C Client : MEW / KUWAIT CONTROLS |
|
Maintenance of Boiler Feed Water Pumps,F.D.Fans, all types of Valves from 2" to 48" in Mina Al-zour Power Station. |
1994-1995 10 months |
1994-1995 10 months |
Mecahnical Electrical |
|
14 |
Project : MC/1099-94/95 SC-2030 Client : MEW-SHUAIBA SOUTH POWER STATION |
|
Annual Maintenance of Instrument & Control System for Power and Distillation Plants. |
1994-1995 (12 months) |
1994-1995 (12 months) |
Instrumentation |
|
15 |
Project : RRP-SC-12 SC-2028 Client : CPECC / KNPC-MAA |
|
Removal, Cleaning, Repairing, Reassembling and Testing of Control Valves, Motor Operated Valves, Pneumatic Valves, Gate Valves, Ball Valves, etc, in association with M.F.Kent, UK. |
1994-1995 (10 months) |
1994-1995 (10 months) |
Mecahnical Instrumentation |
|
16 |
Project : 242-91/92 Client : MEW - AL-ZOUR |
|
Maintenance work of medium & low voltage switchgears & motors of 3 power units. |
1992-1993 (24 months) |
1992-1993 (24 months) |
Electrical |
|
17 |
Project : CS-080 SC-2018 Client : KNPC-S |
|
Service & Maintenance of theFire Alarm System at Shuaiba Refinery. |
1990-1993 (36 months) |
1990-1993 (36 months) |
Electrical |
|
18 |
Project : FCC-102 SC-2024 Client : BECHTEL / KOC |
|
Repair and Maintenance of Fire Protection Equipments & Panels. |
1990-1993 12 months |
1990-1993 12 months |
Electrical |